Name of the Project |
Kandiya Mini Hydel Project (10MW) |
Type |
Run-of-River type Hydro Project. Only Diversion Structure (gated) without Storage requirement |
Location and River |
Across Bhadra River near Kalasa, Chikmagalur |
Current Execution Status |
- Project Identification, Pre-feasibility, DPR, License, land acquisition, tendering already done.
|
Status of various Clearances |
Project license received. Clearances are in progress |
Evacuation Corridor |
66 kv transmission line to be built to evacuate to nearby Sub-Station |
Land acquisition Status |
Land identification complete and land acquisition agreement is reached |
Start of Operations date |
EPC Works are scheduled to commence in August 2015 and complete by October 2017 |