Project Model |
Shahapur |
Location |
Sattegala village, Kollegala Taluk |
District / State |
Chamarajnagar, Karnataka |
Development type |
Run of the river plant utilizing head at the location. |
Installed capacity |
6.25 MW (4x1.563) |
River Stream / Canal |
River Cauvery |
Water conductor system |
Diversion structure , Forebay, Intake structure, Power house and tailrace channel |
Penstock |
Inlet pipe of 4mtr dia x 6mtr length |
Turbines |
Vertical full Kaplan |
Rated Discharge |
37.52 cumecs |
Rated Head |
5 mtr |
Generators |
Synchronous |
Power house |
42m (L) x 21m (W) x 19.6m (H) |
Date of Commissioning |
June 2007 |
Annual Generation Potential |
35.3 Mu |
Transmission line (already setup by BPCL) |
66KV Double circuit transmission line to Sattegala Substation about 2kms length |